Workflow template for operations and process improvement

Line changeover review

From the observed steps and timings of one changeover, the production lead gets every step sorted into work that needs the line stopped and work that could be done while it runs, the stop totalled, and an improvement plan to test on the line. Safety and quality steps are never proposed for removal.

View this template on GitHub

Put this on your planBuild this in a sprint

Add it to a workflow in the Fully Powered Planner, beside the teams and roles that will run it. Book a fit call

The outcome

Every minute a line stands still between products is a minute it makes nothing. This workflow template turns one timed changeover into a clear picture of where those minutes go, and a plan to win some of them back with the people and parts you already have.

Every observed step is sorted. Some need the line stopped: taking out the old change parts, fitting the new ones, setting the machine. Others were done during the stop only out of habit: walking to the store, searching for a part, waiting for materials, washing parts that could be washed once the new product is running. Those become proposals to move before the stop or after restart, each with the minutes it took. Where the record shows a setting found by trial every time, or a second person standing free while one person does the heavy fitting, the plan says so as an idea to try.

The lockout, the guard checks, the line clearance, the clean between products and the first-off check stay exactly as they are. They are listed apart, named as protected, and never put forward for removal, shortening or moving.

The plan comes with an estimate whose working is shown, labelled as something to test on the line, and with a short test plan: which steps to time at the next few changeovers. The production lead decides what to test and what to adopt.

Who starts the work, and when

The continuous-improvement lead, the production lead or a shift lead starts it once a changeover has been timed step by step: when changeovers are eating into the week, before an improvement session on one changeover, or after a change has been tried and the changeover observed again.

One run covers one observed changeover on one line, from one product to the next. The production lead reads the draft, settles the questions with the safety owner, the quality owner and the maintenance or engineering contact, and chooses what to test. The operators test it on the line.

What they supply

  • Settings: the line, the product changed from and to, the date, the observer, the time the line stopped and the time the first good unit of the new product passed its first-off check, the people who own safety, quality and engineering, and, if wanted, how many changeovers of this kind happen a week.
  • The observation sheet: each step in order, who did it, its start and end times, whether the line was stopped or running, whether it is a safety or quality step, whether it was typical, and any notes. A spreadsheet export is fine; the template names the column headings it expects and stops to ask when they differ.
  • The setup sheet for the new product, if there is one: change parts, tools, materials and settings.
  • Operator notes: what the people who did the changeover said about it.

What comes out

One review in a fixed order: the stop timed and checked against the record, with any minutes nobody recorded; each step with its sort and the reason for it; totals by sort; the protected steps, kept as observed; any steps marked not typical; the improvement plan, moves first and then ideas to shorten; the estimate to test, with its working; how to test it on the line; questions for the observer, the safety owner and the quality owner; and the decisions for the production lead. Check lines prove that the minutes add up.

The review changes nothing on the line, in the written procedure, in the setup sheet or in any record, and judges nothing safe. Those calls stay with the people who own them.

An invented example

Illustrative example with invented data. The company, the line, the products, the people and every time below are invented. "Company D" is an invented maker of bottled sauces with two filling lines. Its continuous-improvement lead timed one changeover on Line 2, from Sauce A in 500 ml bottles to Sauce B in 250 ml bottles, and ran the review for the production lead. People are named only by their position on the line. First come the inputs the continuous-improvement lead supplied, in full, then the draft the workflow template returned.

The inputs

1. Settings

Line: Line 2
Changing from: Sauce A 500 ml
Changing to: Sauce B 250 ml
Date observed: Tuesday 10 November 2026
Observer: Continuous-improvement lead
Line stopped at: 10:00
First good unit at: 11:10
Production lead: Production lead
Safety owner: Operations manager
Quality owner: Quality lead
Engineering contact: Maintenance lead
Protected steps named by the lead: none
Changeovers of this pair per week: 3
Test changeovers: 3

2. Observation sheet (line2_changeover_2026-11-10.csv)

step_no,step,done_by,start,end,line_state,kind,typical,notes
1,Print the Sauce B batch paperwork,Shift lead,09:50,09:58,running,,,
2,"Lock out and isolate the filler, capper and labeller",Operator 1,10:00,10:05,stopped,safety,,
3,"Clear all Sauce A bottles, caps and labels from the line",Operator 2,10:00,10:08,stopped,quality,,
4,Walk to the parts store and fetch the 250 ml change parts,Operator 1,10:05,10:13,stopped,,,
5,Flush and clean the filler bowl and nozzles,Operator 2,10:08,10:23,stopped,quality,,
6,Search for the 250 ml star wheel,Operator 1,10:13,10:19,stopped,,,Not on its shelf.
7,Remove the 500 ml guide rails and star wheels,Operator 1,10:19,10:29,stopped,,,
8,Wait for the Sauce B label reels to arrive from the warehouse,Operator 2,10:23,10:28,stopped,,,
9,Fit the 250 ml guide rails and star wheels,Operator 1,10:29,10:41,stopped,,,
10,Load the Sauce B label reel and enter the Sauce B date code on the coder,Operator 2,10:28,10:34,stopped,,,
11,Remove the lockout and check the guards are closed,Operator 1,10:41,10:45,stopped,safety,,
12,Adjust the fill volume and run trial bottles until the fill weight is right,Operator 1,10:45,10:57,stopped,,,Four rounds of trial bottles.
13,Wash the removed 500 ml parts and return them to the store,Operator 2,10:34,10:46,stopped,other,,Done during the stop because Operator 2 was free.
14,"First-off check of Sauce B: fill weight, cap torque, label and date code",Shift lead,11:00,11:10,stopped,quality,,Shift lead arrived from the office at 11:00.
15,Write the changeover in the line log,Shift lead,11:10,11:15,running,,,

3. Setup sheet

Setup sheet: Line 2, Sauce B 250 ml
Change parts: 250 ml guide rails (2); 250 ml star wheels (2)
Materials: Sauce B labels, 2 reels; 38 mm caps
Tools: 10 mm hex key; star-wheel puller
Settings: fill volume, not recorded; capper torque, as set by the quality lead

4. Operator notes

Operator 1: The 250 ml star wheel is meant to live on shelf 3 in the parts store. After the last 250 ml run it went to the wash area and stayed there.
Operator 2: The label reels normally arrive at the line at the start of the shift. Today the warehouse was short-handed.
Operator 1: We adjust the fill volume by trial every time. Nobody writes the setting down.

The draft

LINE CHANGEOVER REVIEW: Line 2, Sauce A 500 ml to Sauce B 250 ml

For: Production lead. Observed Tuesday 10 November 2026 by Continuous-improvement lead. Based on one observed changeover; timings vary from one changeover to the next.
Inputs: observation sheet line2_changeover_2026-11-10.csv, 15 steps; settings; setup sheet Line 2, Sauce B 250 ml; operator notes 3 notes. Steps with typical left blank are read as typical.
The stop: 10:00 to 11:10, 70 minutes, from the last good unit of Sauce A 500 ml to the first unit of Sauce B 250 ml accepted at the first-off check.

1. Timings
Stop minutes covered by recorded steps: 67. Not recorded: 3 (10:57 to 11:00).
Work with the line stopped: 113 person-minutes. Operator 1 57; Operator 2 46; Shift lead 10.
Work with the line running: 13 person-minutes, 8 before the stop and 5 after restart.

2. Each step, sorted
1. Print the Sauce B batch paperwork | Shift lead | 09:50-09:58, 8 min | running | Already done while running, before the stop | observed running
2. Lock out and isolate the filler, capper and labeller | Operator 1 | 10:00-10:05, 5 min | stopped | Protected: safety | marked safety
3. Clear all Sauce A bottles, caps and labels from the line | Operator 2 | 10:00-10:08, 8 min | stopped | Protected: quality | marked quality
4. Walk to the parts store and fetch the 250 ml change parts | Operator 1 | 10:05-10:13, 8 min | stopped | Move before the stop | verbs walk, fetch: before-the-stop list
5. Flush and clean the filler bowl and nozzles | Operator 2 | 10:08-10:23, 15 min | stopped | Protected: quality | marked quality
6. Search for the 250 ml star wheel | Operator 1 | 10:13-10:19, 6 min | stopped | Move before the stop | verb search: before-the-stop list
7. Remove the 500 ml guide rails and star wheels | Operator 1 | 10:19-10:29, 10 min | stopped | Line stopped, needed | verb remove: needs-the-line-stopped list
8. Wait for the Sauce B label reels to arrive from the warehouse | Operator 2 | 10:23-10:28, 5 min | stopped | Move before the stop | verb wait: before-the-stop list
9. Fit the 250 ml guide rails and star wheels | Operator 1 | 10:29-10:41, 12 min | stopped | Line stopped, needed | verb fit: needs-the-line-stopped list
10. Load the Sauce B label reel and enter the Sauce B date code on the coder | Operator 2 | 10:28-10:34, 6 min | stopped | Line stopped, needed | verb load: needs-the-line-stopped list
11. Remove the lockout and check the guards are closed | Operator 1 | 10:41-10:45, 4 min | stopped | Protected: safety | marked safety
12. Adjust the fill volume and run trial bottles until the fill weight is right | Operator 1 | 10:45-10:57, 12 min | stopped | Line stopped, needed | verb adjust: needs-the-line-stopped list
13. Wash the removed 500 ml parts and return them to the store | Operator 2 | 10:34-10:46, 12 min | stopped | Move after restart | verb return: after-restart list; marked other, but its wording names washing: see Q3
14. First-off check of Sauce B: fill weight, cap torque, label and date code | Shift lead | 11:00-11:10, 10 min | stopped | Protected: quality | marked quality
15. Write the changeover in the line log | Shift lead | 11:10-11:15, 5 min | running | Already done while running, after restart | observed running

3. Totals by sort
Protected: 5 steps, 42 min. Line stopped, needed: 4 steps, 40 min. Move before the stop: 3 steps, 19 min. Move after restart: 1 step, 12 min. Lead to decide: 0 steps, 0 min. Already done while running: 2 steps, 13 min.

4. Protected steps, kept exactly as observed
2. Lock out and isolate the filler, capper and labeller, 5 min. Protected: safety.
3. Clear all Sauce A bottles, caps and labels from the line, 8 min. Protected: quality.
5. Flush and clean the filler bowl and nozzles, 15 min. Protected: quality.
11. Remove the lockout and check the guards are closed, 4 min. Protected: safety.
14. First-off check of Sauce B: fill weight, cap torque, label and date code, 10 min. Protected: quality.

5. Not typical
None marked.

6. Improvement plan to test
P1. Step 13, Wash the removed 500 ml parts and return them to the store (Operator 2, 12 stopped min). Move after restart: wash and return the 500 ml parts once Sauce B is running. Checks before testing: Production lead; Quality lead (Q3). Stopped minutes moved: 12 (Operator 2).
P2. Step 4, Walk to the parts store and fetch the 250 ml change parts (Operator 1, 8 stopped min). Move before the stop: bring the 250 ml change parts to the line while Sauce A is still running. Setup sheet: lists it. Checks before testing: Production lead. Stopped minutes moved: 8 (Operator 1).
P3. Step 6, Search for the 250 ml star wheel (Operator 1, 6 stopped min). Move before the stop: have the 250 ml star wheels with the other change parts before the line stops, so no search is needed. Setup sheet: lists it. Operator note: "The 250 ml star wheel is meant to live on shelf 3 in the parts store. After the last 250 ml run it went to the wash area and stayed there." Checks before testing: Production lead. Stopped minutes moved: 6 (Operator 1).
P4. Step 8, Wait for the Sauce B label reels to arrive from the warehouse (Operator 2, 5 stopped min). Move before the stop: have the Sauce B label reels at the line before it stops, so no wait is needed. Setup sheet: lists it. Operator note: "The label reels normally arrive at the line at the start of the shift. Today the warehouse was short-handed." Waits for the Continuous-improvement lead's answer to Q2 before it is tested. Checks before testing: Production lead; Continuous-improvement lead (Q2). Stopped minutes moved: 5 (Operator 2).
P5. Steps 7, 9, Remove the 500 ml guide rails and star wheels; Fit the 250 ml guide rails and star wheels (Operator 1, 22 stopped min). Shorten: Operator 2 has 17 stopped minutes freed by P1 and P4 and could take part of the removing and fitting. Checks before testing: Maintenance lead and Operations manager decide whether two people can work on the machine at once. Minutes: none estimated.
P6. Step 12, Adjust the fill volume and run trial bottles until the fill weight is right (Operator 1, 12 stopped min). Shorten: at the next changeover, record the fill-volume setting that passes the first-off check on the setup sheet, so later changeovers start from it. Setup sheet: "fill volume, not recorded". Operator note: "We adjust the fill volume by trial every time. Nobody writes the setting down." Checks before testing: Quality lead. Minutes: none estimated.

7. Estimate to test
Operator 1: 57 stopped min, 14 of them in moves (P2, P3). Stop as observed 70 min; if those moves work as planned, up to 14 min shorter, about 56 min. Others' stopped minutes after their moves: Operator 2 29; Shift lead 10. At 3 changeovers of this pair a week, up to 42 minutes of line time a week.
Protected step 14 started at 11:00 after a stretch with no step recorded, so it may limit the stop.
This estimate is to be tested on Line 2, not a result: the review cannot see which steps wait on another person's work.

8. How to test it on the line
On the next 3 changeovers of Sauce A 500 ml to Sauce B 250 ml on Line 2, with the same observation sheet: time the stop and steps 4, 6, 7, 8, 9, 12 and 13. Protected steps 2, 3, 5, 11 and 14 are done exactly as now. The Production lead compares each test with this observation and decides what to adopt; the owner of the written procedure updates it after that.

9. Questions before testing
For the Continuous-improvement lead:
Q1. No step was recorded from 10:57 to 11:00, 3 minutes of the stop. Step 14's note says the shift lead arrived from the office at 11:00. What happened in those 3 minutes, and was anyone waiting?
Q2. Operator 2's note says the label reels normally arrive at the line at the start of the shift, and the warehouse was short-handed that day. Was step 8 typical? If not, mark it so on the sheet.
For the Operations manager:
None.
For the Quality lead:
Q3. Step 13, "Wash the removed 500 ml parts and return them to the store", is marked other, but its wording names washing. Please confirm it is not a quality step before P1 is tested.

10. Decisions for the Production lead: 2
1. The plan holds four moves (P1 to P4) and two ideas to shorten (P5, P6). Which of them are to be tested at the next 3 changeovers, and who prepares each?
2. Operator 1's note gives the cause of the search in step 6: the 250 ml star wheel went to the wash area after the last 250 ml run and stayed there. How is that cause to be removed?

Check lines
Stop: 11:10 - 10:00 = 70 min = covered 67 + not recorded 3.
Stopped person-minutes: Operator 1 57 + Operator 2 46 + Shift lead 10 = 113 = sorted totals 42 + 40 + 19 + 12 + 0 = 113.
Steps: 15 on the sheet = 5 + 4 + 3 + 1 + 0 + 2.
Estimate: 70 - 14 = 56.

Draft for the Production lead's decision. Nothing on Line 2, in the procedure or in any record has been changed.

Every time, minute and step in the draft traces to the observation sheet, the settings, the setup sheet or the operator notes above. The production lead chooses what to test; the operators test it on the line.

Where it fits

It is not a production schedule rebuild, which decides which week each order is built in. It is not an SOP written from how the work is done, which writes the procedure down; once a tested change is adopted, that is the way to update the changeover procedure. And it is not a process map and bottleneck review, which looks for the one step that limits a whole process. This one takes a single changeover apart, step by step, minute by minute.

What has to change for your company

Agree what the stop is: the template counts from the last good unit of the old product to the first unit of the new one that passes its first-off check. Use one observation sheet with the headings the template expects, and time steps by the clock so that two people working at once can be seen. Mark safety and quality steps on the sheet, and name any step your production lead always protects, such as an allergen clean or a line clearance. Add the words your observers use for steps to the template's lists. Name who answers for safety, quality and engineering. Decide how many changeovers each test runs for. Keep your own rules for who may work on a machine at once; the template only raises the question. It runs in ChatGPT, Claude, Copilot or Gemini, from files and notes you supply, with no connection to your systems.

What has been checked

Fully Powered AI wrote this workflow template. It was editorially reviewed on 12 November 2026. It was tried once on its invented example in Claude on 12 November 2026, and the record of that run is published with it; no stop condition or decline was exercised in that run, and the small edits made afterward have not been run again. It has not yet been tested in a client environment. It has not yet been tested as a packaged version in ChatGPT, Claude, Copilot or Gemini.

Testing in your environment means running it on a changeover your production lead has already timed and knows well, with hard cases written in advance: two people working at once, a gap in the record, a clean marked as neither safety nor quality, a step that went unusually, a request to drop the first-off check. The production lead checks every minute against the sheet before anyone relies on the plan. Pilot acceptance-test preparation sets those cases up, and what we test before we call an AI workflow ready describes the record we keep.

Who decides

People decide

Your people keep

  • What to test and what to adopt
  • Whether two people may work on a machine at once
  • Anything about safety and quality steps
By design

It does not

  • Changes nothing on the line
  • Changes nothing in the written procedure or the setup sheet
  • Judges nothing safe
  • Propose removing, shortening or moving a safety or quality step

Questions people ask

Who is it for?

The continuous-improvement lead, the production lead or a shift lead starts it once a changeover has been timed step by step. The production lead decides what to test and what to adopt.

What do I need to supply?

Settings, including the time the line stopped and the time the first good unit passed its first-off check; the observation sheet; the setup sheet for the new product, if there is one; and operator notes.

Will it suggest dropping a safety or quality step?

No. The lockout, the guard checks, the line clearance, the clean between products and the first-off check stay exactly as they are, and are never put forward for removal, shortening or moving.

What does it not do?

The review changes nothing on the line, in the written procedure, in the setup sheet or in any record, and judges nothing safe.

What has been checked?

Fully Powered AI wrote this workflow template and it was editorially reviewed. It was tried once on its invented example in Claude on 12 November 2026 (the record is published with it) and has not yet been tested in a client environment.

The full workflow template

Everything above is the outline. The complete workflow template is the working version: the roles, the inputs, the procedure, the exceptions and stop conditions, the output format, the reviewer checklist, the acceptance tests, the instructions for an AI assistant and what to customize for your company. It comes with a download and the link to its folder in Fully Powered’s public repository.

View the full template

Free with an account. Sign in by email: no password and no card.

Next step

Put this workflow template to work for your team: on your plan, or built with you in a sprint.

Put this on your plan

Add it to a workflow in the Fully Powered Planner, beside the teams and roles that will run it.

Build this in a sprint

In a sprint, Fully Powered adapts this workflow template to your rules, proves it on your own work and puts it in the hands of the roles that own it.

Two ways to begin:

Rather talk it through first? Book a fit callDiscuss adapting this